Erosion Control Practices
NDOT
Author
07/12/2024
Added
28
Plays
Description
Erosion Control Practices
Searchable Transcript
Toggle between list and paragraph view.
- [00:00:00.090]Section 2
- [00:00:00.923]of this online installer certification course
- [00:00:03.030]covers erosion control practices.
- [00:00:05.520]We'll cover 10 different erosion control types
- [00:00:08.100]and some of the various techniques
- [00:00:09.540]and practices utilized for each one.
- [00:00:12.450]In this installer training section for erosion controls,
- [00:00:15.150]we'll discuss the following.
- [00:00:16.950]Seeding specifications for permanent, cover crop,
- [00:00:20.370]and temporary types, including slope protection,
- [00:00:23.100]a specific type of seeding method.
- [00:00:25.350]Also, to support germination of seeding operations,
- [00:00:28.410]we'll cover fertilizing and soil amendments.
- [00:00:31.290]In addition, we will cover methods
- [00:00:33.240]to stabilize bare soil using sodding, mulching, hydromulch,
- [00:00:38.220]soil retention blankets, transition mats, silt checks
- [00:00:41.700]for slopes using wattles, slope tracking,
- [00:00:44.580]temporary slope drains, and soil roughening.
- [00:00:48.000]First, let's review seeding and vegetation.
- [00:00:50.760]Universal rules of thumb for vegetation
- [00:00:52.680]would be, retain existing vegetation as long as possible.
- [00:00:57.000]It's the most effective erosion control we have.
- [00:01:00.120]Establish new vegetation as quickly as possible,
- [00:01:03.450]and as always, minimize the amount
- [00:01:05.130]of time soil is exposed on a construction site.
- [00:01:08.640]Proper seed bed preparation is critical
- [00:01:10.680]to the success of any type of seeding job.
- [00:01:13.230]Seed bed preparation should be done
- [00:01:14.910]according to the soil type
- [00:01:16.590]and whether the seeding is temporary or permanent.
- [00:01:19.380]Seeding will require finely-graded slopes
- [00:01:21.510]and ditches that have loose soil to specify depths.
- [00:01:24.660]Because of that, seeding and mulching
- [00:01:26.250]should happen as soon as possible
- [00:01:27.600]to minimize exposure
- [00:01:28.740]of the finely-graded area to potential erosion.
- [00:01:32.250]The most important aspect of any NDOT project
- [00:01:35.040]is to establish vegetation as quickly as possible.
- [00:01:38.490]Let's start off by discussing permanent seeding.
- [00:01:41.010]This is seeding done as final grade is achieved,
- [00:01:43.620]placed as part of the permanent erosion control plan.
- [00:01:46.740]Permanent seeding must be done within the planting seasons
- [00:01:49.230]of March 1st to June 15th and August 1st to December 1st.
- [00:01:53.520]Seeding must not be done on frozen, wet, or untillable.
- [00:01:56.940]We'll talk about proper seed bed preparation
- [00:01:59.070]at frequent points in this section.
- [00:02:01.170]For permanent seeding, surface roughening should be done
- [00:02:03.630]to break up compaction of the top three inches of soil.
- [00:02:06.840]Do this within five days of sowing permanent seed.
- [00:02:10.200]There are two main types of permanent seeding applications
- [00:02:12.720]that are done on NDOT projects,
- [00:02:14.970]broadcast seeding and drill seeding.
- [00:02:17.610]The site conditions and seeding selection will dictate
- [00:02:20.100]which method of application will work best for the job.
- [00:02:22.650]For broadcast seeding,
- [00:02:23.910]a harrowing of the soil surface happens first.
- [00:02:26.640]Then the seed is applied prior to any mulches
- [00:02:28.860]or blankets being installed for erosion control,
- [00:02:31.740]because the chances are greater for seed
- [00:02:33.450]to have less than adequate soil contact and protection.
- [00:02:36.780]Broadcast applications should be used
- [00:02:38.520]only where equipment access is limited.
- [00:02:41.220]For drill seeding, apply the seed
- [00:02:42.930]with properly calibrated equipment prior to installation
- [00:02:45.690]for mulches or soil retention blankets.
- [00:02:48.540]In addition to the two main types described,
- [00:02:50.940]NDOT specifies hydraulic seeding,
- [00:02:53.220]which is only allowed in approved, special conditions.
- [00:02:56.940]NDOT specifies different seed types for permanent seeding.
- [00:03:00.840]Type A includes back slopes, ditches,
- [00:03:03.090]and portions of the forest slopes.
- [00:03:05.130]Type B includes shorter plant varieties
- [00:03:07.110]placed on shoulder areas and in the medians,
- [00:03:09.270]which are frequently mowed.
- [00:03:11.040]Type C includes other seed mixtures
- [00:03:12.870]as needed for special placement.
- [00:03:14.340]For permanent seed and for each seeding type,
- [00:03:16.470]we'll discuss.
- [00:03:17.460]The seed bags must include NDOT seed tags.
- [00:03:20.880]Bulk seed is allowed,
- [00:03:22.440]but a purity and germination test is required for approval
- [00:03:25.350]before the seed is used.
- [00:03:27.180]The seed shall be delivered to the project
- [00:03:28.980]with tags attached to the bags.
- [00:03:31.230]The seed shall not be used until the project engineer
- [00:03:33.750]or designated project representative
- [00:03:36.060]collects the tags from the bag immediately prior to use.
- [00:03:39.570]Unless this tag collection happens,
- [00:03:41.250]a contractor may not be paid for seeding.
- [00:03:44.280]With all seeding operations
- [00:03:45.810]and particularly permanent seeding jobs,
- [00:03:48.270]communication is key
- [00:03:49.320]between NDOT project staff and contractors.
- [00:03:52.680]Remember the specified planting seasons
- [00:03:54.870]and always take the time to prepare the area
- [00:03:56.970]to take the permanent seeding
- [00:03:58.140]to provide optimum germination conditions.
- [00:04:00.900]Permanent seeding doesn't have to wait
- [00:04:02.430]until the entire project is completed.
- [00:04:05.010]Permanent seeding can be
- [00:04:06.420]and is encouraged to be initiated on any portion
- [00:04:08.760]of a project once the final grade is achieved.
- [00:04:12.060]Cover crop seeding is a type
- [00:04:13.470]that is done for temporary erosion
- [00:04:15.390]and sediment control while the project is still ongoing.
- [00:04:19.260]Cover crop seeding is done in phased construction areas,
- [00:04:22.050]surcharge areas, other disturbed areas
- [00:04:24.390]that had not been permanently seeded,
- [00:04:26.400]or as directed by the project manager.
- [00:04:29.100]For cover crop seeding, the goal is to sow seed
- [00:04:31.680]that has a good chance of establishing quickly,
- [00:04:33.660]such as oats or annual rye.
- [00:04:35.880]The cover crop seed selected is typically
- [00:04:37.890]a rapidly-germinating variety
- [00:04:40.020]used for short spurts where vegetation is needed,
- [00:04:42.930]but not for an extended period of time.
- [00:04:45.510]For finished grades, cover crop seeding needs
- [00:04:47.820]to be started within 24 hours
- [00:04:50.010]and completed within seven days
- [00:04:51.450]of finish grading work.
- [00:04:52.650]For cover crop seeding, there are early season,
- [00:04:55.350]mid-season, and late season mixes available
- [00:04:58.650]from oats and millet in the spring
- [00:05:00.300]and early summer to winter wheat in the fall.
- [00:05:03.330]Annual ryegrass applied only in urban areas
- [00:05:05.940]is available year round.
- [00:05:07.920]Also, note that broadcast
- [00:05:09.510]and drill seeding application rates
- [00:05:11.130]are the same For cover crop seeding.
- [00:05:12.870]Is the placement of cover crop seed alone
- [00:05:14.790]considered stabilization?
- [00:05:16.680]No.
- [00:05:17.513]However, once it's germinated and established,
- [00:05:20.250]cover crop seeding provides
- [00:05:21.570]the same short-term effect as permanent vegetation.
- [00:05:24.660]It's an important distinction to make,
- [00:05:26.250]as the State Of Nebraska's construction general permit
- [00:05:29.130]requires the initiation of temporary stabilization
- [00:05:31.710]of exposed soils exposed for 14 days
- [00:05:34.110]or more due to site and activity.
- [00:05:36.330]This is required even if site will be temporarily inactive.
- [00:05:39.870]Seeding alone doesn't achieve this until it's established.
- [00:05:43.020]At a minimum, when soil and weather conditions exist,
- [00:05:45.570]that it's anticipated that the cover crop seed
- [00:05:47.700]will not germinate within 10 calendar days,
- [00:05:49.860]the project manager or her construction engineer
- [00:05:52.290]will direct the temporary mulch be applied.
- [00:05:55.080]If it fails to germinate
- [00:05:56.310]or produce vigorous growth,
- [00:05:58.050]reseeding shall be required at the contractor's expense.
- [00:06:01.830]Temporary seeding consists of furnishing
- [00:06:03.810]and applying seed to soil that would be difficult
- [00:06:05.940]to seed using broadcast or drill seeding methods.
- [00:06:09.120]Temporary seeding requires hydroseeding,
- [00:06:11.670]a technique we will discuss in a little bit.
- [00:06:14.100]Temporary seeding can be used on embankments
- [00:06:16.230]or cuts that are temporary in nature,
- [00:06:18.270]soil stockpiles and other places that require stabilization.
- [00:06:22.080]The work of temporary seeding shall be started
- [00:06:24.030]within 24 hours and completed within seven calendar days,
- [00:06:27.180]following earth-moving activities.
- [00:06:30.000]Fertilizer may be specified on certain seeding projects,
- [00:06:33.270]primarily for permanent seeding.
- [00:06:35.490]These may be synthetic, organic,
- [00:06:37.080]or inorganic fertilizers,
- [00:06:39.120]fertilized prior to seeding and worked into the soil.
- [00:06:42.150]Payment for fertilizing is subsidiary
- [00:06:43.980]to items requiring fertilization.
- [00:06:46.860]For application of fertilizers,
- [00:06:48.510]apply uniformly with approved mechanical spreaders
- [00:06:51.060]at rates specified in the project contract.
- [00:06:53.940]Do not apply fertilizers within 50 feet
- [00:06:55.980]of any wetland, lake, or stream.
- [00:06:58.740]For soil incorporation with permanent seeding,
- [00:07:01.470]fertilization application should happen
- [00:07:03.240]prior to seeding.
- [00:07:04.530]In conjunction with any seed, be prep work,
- [00:07:07.110]but should not be worked into the soil
- [00:07:08.790]any deeper than three inches.
- [00:07:10.230]Soil amendments are a new specification for NDOT
- [00:07:13.590]and generally refer to products
- [00:07:15.000]known as hydraulic growth mediums.
- [00:07:17.310]These products are made from a combination of ingredients
- [00:07:19.680]for improving poor soil conditions such as processed straw,
- [00:07:23.460]flexible flax fibers, peat moss, plant root fungi,
- [00:07:26.940]and other proprietary ingredients.
- [00:07:28.740]These particular soil amendments may be specified
- [00:07:31.320]for permanent seeding projects.
- [00:07:33.450]When specified, drill half of the seed required
- [00:07:35.730]per acre of the project area,
- [00:07:37.650]then apply the other half of the required seed
- [00:07:39.600]by incorporating into the soil amendment slurry.
- [00:07:42.660]Apply within 24 hours of seed planting
- [00:07:45.030]and uniformly over the prepared area
- [00:07:46.920]at an application rate of two tons per acre.
- [00:07:50.280]Sodding is treated as a permanent erosion control
- [00:07:52.590]providing instant coverage on exposed soils,
- [00:07:55.320]making it one of the most effective
- [00:07:56.820]erosion controls available.
- [00:07:58.830]Sodding involves laying a continuous cover
- [00:08:00.900]of grass sod on exposed soils.
- [00:08:03.990]With sodding installations,
- [00:08:05.760]watering is required for 30 days after insulation.
- [00:08:09.030]If it's not green and healthy
- [00:08:10.470]after 30 days, it should likely be rejected
- [00:08:12.660]and reinstalled by the contractor,
- [00:08:14.760]which must also be watered for 30 days.
- [00:08:17.580]In this example, the sod is not only very brown,
- [00:08:20.700]signaling a lack of moisture,
- [00:08:22.530]but it also has large cracks between the sod strips.
- [00:08:25.710]This installation should likely be rejected
- [00:08:28.230]and the contractor should be forced
- [00:08:29.670]to reinstall new sod at their own expense.
- [00:08:32.610]Soil amendments may also need
- [00:08:34.110]to be considered if the soil the sod is being installed
- [00:08:37.200]into is poor or lacking organic content.
- [00:08:40.830]Next, let's move on to mulching.
- [00:08:43.080]As we discussed briefly in the previous module,
- [00:08:45.660]the purpose of erosion control
- [00:08:47.190]is to prevent the erosion process from beginning,
- [00:08:49.890]starting with protecting the soil surface
- [00:08:51.780]from the impact of raindrops.
- [00:08:53.910]Mulching covers the soil surface, reducing rainfall impacts
- [00:08:57.330]and helps to absorb and hold moisture near the surface.
- [00:09:00.750]Applied after seeding,
- [00:09:02.130]mulch protects the seed underneath
- [00:09:03.750]during the germination process.
- [00:09:05.880]When used alone, it temporarily protects the soil surface
- [00:09:08.790]between specified planting seasons per NDOT specifications.
- [00:09:12.990]Acceptable mulch types include
- [00:09:15.240]dry cured native prairie hay,
- [00:09:17.010]native grass hay, and straw from oats, wheat or rye.
- [00:09:21.240]NDOT does not accept the following mulch materials:
- [00:09:24.750]Broome hay, rushes, cattails, reed canary grass,
- [00:09:28.830]wide-bladed grass or any invasive species.
- [00:09:32.040]All mulch must be certified noxious
- [00:09:34.110]and or weed-free by a county weed authority
- [00:09:36.150]or other approved agent.
- [00:09:38.490]An important skill for an installer
- [00:09:40.110]is to visually confirm the proper mulching application rate.
- [00:09:43.530]Here we have four examples of coverage
- [00:09:45.300]with a corresponding application rate.
- [00:09:47.700]Typically, the installation specification
- [00:09:49.710]will be for a rate of two tons per acre.
- [00:09:52.290]At that application rate,
- [00:09:53.610]it should be very difficult to see any soil surface
- [00:09:56.040]as you're looking down at any given location.
- [00:09:58.740]More than likely, you will see application rates
- [00:10:00.840]less than at two tons per acre.
- [00:10:03.210]Whether it is an installation problem
- [00:10:04.920]or due to windy conditions
- [00:10:06.150]that may have blown some of the mulch away,
- [00:10:08.280]make sure to note
- [00:10:09.113]whether or not you believe the proper application rate
- [00:10:11.400]was used when you were conducting
- [00:10:12.810]or observing the installation.
- [00:10:14.250]Specifications will also require proper crimping
- [00:10:16.890]of the straw mulch into the soil,
- [00:10:18.450]typically to a one-to-two inch depth.
- [00:10:20.820]Look for mulch fibers
- [00:10:21.900]that have been driven into the ground deep
- [00:10:23.490]and stand almost vertical in places.
- [00:10:26.250]In lieu crimp straw mulch,
- [00:10:28.230]a tackifier and bonded fiber matrix
- [00:10:30.540]may be specified in some places.
- [00:10:32.940]We'll talk more about those examples coming up.
- [00:10:35.640]Most importantly, to ensure good consistent coverage,
- [00:10:38.640]an installer should avoid applying straw mulch
- [00:10:40.770]in windy conditions if at all possible.
- [00:10:43.950]Even in one project area,
- [00:10:45.780]we can have the potential for inconsistent cover traits.
- [00:10:48.960]The area in the foreground looks
- [00:10:50.310]to have good consistent coverage.
- [00:10:52.530]As we progress further into the project,
- [00:10:54.810]the coverage becomes more inconsistent,
- [00:10:57.150]with only a very thin mulch layer in the distance.
- [00:11:00.120]Consistency with the mulch layer
- [00:11:01.980]following the mulch density to the specification
- [00:11:04.200]as close as possible is what we are looking for.
- [00:11:07.860]Slope protection refers to a specific type
- [00:11:10.110]of installation combination of placing seed
- [00:11:12.270]and a protected covering of mulch on completed shoulders,
- [00:11:15.000]side slopes, ditch bottoms, or back slopes.
- [00:11:18.120]Straw is not allowed for this application.
- [00:11:20.760]Initial seed should be drill seeded if possible,
- [00:11:23.460]with the remainder broadcast over the installed mulch.
- [00:11:26.400]Secure the mulch with either a specialized punch roller
- [00:11:29.400]or with evenly-spaced soil piles, per the specification.
- [00:11:33.780]The next erosion control practice
- [00:11:35.490]we'll discuss is hydromulch.
- [00:11:37.440]These versatile products are wet applications
- [00:11:39.570]of a combination of seed
- [00:11:40.770]and/or mulch sprayed onto the soil surface.
- [00:11:43.800]They protect previously-planted seabeds
- [00:11:45.780]on slopes and roadsides, covering the soil's surface
- [00:11:48.750]to reduce erosion from rainfall impacts.
- [00:11:51.540]Like straw mulch, they retain moisture at the soil surface.
- [00:11:55.080]Some products are used to anchor mulch
- [00:11:56.880]to the soil surface when crimping is prohibitive.
- [00:11:59.910]Some of these types of hydraulic applications
- [00:12:02.100]can also protect exposed
- [00:12:03.450]areas where sheet flows tend to occur.
- [00:12:06.540]There are many different compositions of hydromulch.
- [00:12:09.300]Locations to apply hydromulch vary by grade, soil type,
- [00:12:13.020]stage of construction,
- [00:12:14.580]combination with other BMPs,
- [00:12:16.560]desired conditions, and chemical composition of materials.
- [00:12:20.310]They provide immediate protection from wind and rain
- [00:12:23.040]and provides more time for vegetation to establish.
- [00:12:26.760]Hydraulic mulches are typically specified in four classes
- [00:12:29.760]for NDOT projects.
- [00:12:31.710]Class HM1 is either a dry or wet pelletized mulch.
- [00:12:35.370]These are used in confined and completely flat areas.
- [00:12:38.700]Class HM2 is wood fiber mulch with a tackifier.
- [00:12:42.240]This application works for gentle slopes,
- [00:12:44.220]3.5 to one or less.
- [00:12:46.410]It's not accepted to use in ditch applications,
- [00:12:48.960]and the lifespan for the application is about three months.
- [00:12:52.410]Allow for 24 hours of precipitation
- [00:12:54.600]for curing time for the mulch to set.
- [00:12:57.120]For bonded fiber matrix or class HM3,
- [00:13:00.180]the product is allowable
- [00:13:01.410]on slopes 2 1/2 to one or less.
- [00:13:04.200]BFM longevity is typically up to six months
- [00:13:07.140]and also requires 24 hours of dry curing time.
- [00:13:10.740]For fiber reinforced matrix,
- [00:13:12.720]the product is allowable on slopes 1 1/2
- [00:13:14.957]to one or less and in ditches with a slope of 2.5% or less.
- [00:13:19.890]FRM longevity is 12 months minimum
- [00:13:22.590]and has little to no curing time,
- [00:13:24.660]meaning it's ready to hold up
- [00:13:25.770]to precipitation as soon as it's applied.
- [00:13:28.590]All application rates for hydromulch are 1.5 tons per acre.
- [00:13:32.430]There are two ways to apply hydromulch.
- [00:13:34.710]The most effective way to ensure adequate
- [00:13:36.600]and uniform material coverage is by using the hose.
- [00:13:39.870]An applicator sprays the material
- [00:13:41.520]down over an accessible area
- [00:13:43.440]and is able to achieve uniform coverage.
- [00:13:45.990]The most efficient application method
- [00:13:47.610]is by using the gun or turret,
- [00:13:49.530]located on the back of larger hydromulch equipment.
- [00:13:52.740]While this application method can be more efficient,
- [00:13:55.470]it doesn't always provide the best application
- [00:13:57.570]to ensure uniform coverage.
- [00:13:59.760]As a rule of thumb,
- [00:14:01.200]if you're able to access the treatment area
- [00:14:03.090]with the hose, by all means, use it.
- [00:14:06.450]Visual confirmation of full mulch coverage
- [00:14:08.430]is essential to the success or failure of an application.
- [00:14:11.820]In this example, it's obvious to see the direction
- [00:14:14.220]that hydromulch was shot from was left to right
- [00:14:16.200]from the back of the machine and not with the hose.
- [00:14:19.410]From the applicator's perspective,
- [00:14:21.360]it may very well have looked like 100% coverage.
- [00:14:24.570]Seeing from the side here,
- [00:14:26.070]we can see that the application
- [00:14:27.450]had a shadowing effect as it hit the soil surface.
- [00:14:30.450]If using the gun or turret,
- [00:14:32.370]do everything you can to apply the hydromulch
- [00:14:34.530]in two directions if at all possible.
- [00:14:37.380]This will ensure an even coverage.
- [00:14:39.090]Hydromulch can also be used for rapid stabilization
- [00:14:41.790]when work has stopped for a period of time
- [00:14:43.530]in certain areas of a project.
- [00:14:45.780]These slopes aren't ready for permanent erosion control
- [00:14:48.270]to be installed, but still pose
- [00:14:50.280]a significant threat for real ankle erosion.
- [00:14:53.400]Applying bonded fiber matrix to provide stabilization
- [00:14:56.250]for a period of time is an effective control.
- [00:14:59.520]Visual confirmation of uniform
- [00:15:01.260]and full application is required.
- [00:15:03.480]If you can still see exposed soil
- [00:15:05.040]after application, you can be sure
- [00:15:07.110]you haven't met the installation specification.
- [00:15:09.720]Remember, for all mulch types,
- [00:15:11.430]the application rate is 1.5 tons per acre.
- [00:15:15.240]Soil retention blankets have been in use
- [00:15:17.220]for many decades on construction sites for erosion control.
- [00:15:20.820]Blankets cover the soil surface
- [00:15:22.380]to reduce erosion from rainfall impact.
- [00:15:25.140]Depending on the product type,
- [00:15:26.610]they also prevent soil erosion
- [00:15:28.470]in high velocity drainage areas.
- [00:15:30.690]Soil retention blankets are typically used in conjunction
- [00:15:33.570]with temporary or permanent seeding,
- [00:15:35.730]covering a seeded area,
- [00:15:37.410]preventing the movement of the planted seed.
- [00:15:39.630]They can absorb and hold moisture near the soil surface.
- [00:15:43.440]Different projects with different slopes
- [00:15:45.090]and conditions will dictate the different types
- [00:15:47.010]of soil retention blankets that are used on a site.
- [00:15:50.010]Projects will use any mixture of materials
- [00:15:51.990]to get the job done right.
- [00:15:53.790]Products are not interchangeable
- [00:15:55.230]because they're specified as an engineered product
- [00:15:57.450]for the design condition.
- [00:15:59.070]For example, a Class 1D straw blanket
- [00:16:01.470]would not be used in a high flow area
- [00:16:03.270]such as a ditch bottom.
- [00:16:04.890]A heavier duty Class 1 or 2 blanket
- [00:16:06.930]would be the proper product in a ditch bottom.
- [00:16:09.870]While there are many NDOT specification types
- [00:16:12.480]for soil retention blankets,
- [00:16:14.310]the primary makeup for Class 1 include
- [00:16:16.770]straw, coconut, fiber, and wood excelsior fiber.
- [00:16:19.980]Some blanket types may also include
- [00:16:21.810]a combination of straw and coconut fiber.
- [00:16:24.690]Also, the blanket netting may vary with certain types.
- [00:16:27.870]A biodegradable nylon netting is common,
- [00:16:30.510]but natural jute or twine fiber netting
- [00:16:32.460]is also used for certain Class 1 blankets.
- [00:16:35.340]The lifespan of Class 1 blankets is anywhere
- [00:16:37.530]from six months to three years depending on the type.
- [00:16:40.726]Class 1 blankets are used on slopes
- [00:16:43.020]and hillsides with a slope steepness of up to three to one.
- [00:16:46.200]They can also be used in shallow, low-slope ditches
- [00:16:49.080]where concentrated runoff velocities are low.
- [00:16:52.230]Different blanket types
- [00:16:53.280]have different installation staple patterns.
- [00:16:55.890]Be sure to follow NDOT specifications for each blanket type.
- [00:17:00.630]Once we cross over into mostly synthetic materials
- [00:17:03.300]that make up a blanket,
- [00:17:04.890]we are referring to Class 2 blankets
- [00:17:07.200]built for permanent, long-term ditch stabilization.
- [00:17:11.070]They can be a combination of synthetic
- [00:17:12.720]and biodegradable materials
- [00:17:14.790]or be composed of 100% synthetic material.
- [00:17:18.210]Because of their higher cost,
- [00:17:19.830]they aren't typically used on side slopes.
- [00:17:22.410]The sturdy nature of these blankets support
- [00:17:24.300]greater root growth media
- [00:17:25.500]and root structure compared to simply bare soil
- [00:17:28.380]or a material that fully biodegrades.
- [00:17:31.530]This cross-sectional view
- [00:17:32.760]of a turf reinforcement map shows the growth media
- [00:17:35.280]in the middle, protected root growth
- [00:17:37.020]and vegetation reinforcement.
- [00:17:39.300]The key here is that the material
- [00:17:40.770]is laid smoothly against the soil surface.
- [00:17:43.740]Any gaps between the fabric material
- [00:17:45.870]and the soil surface will promote scour under the material.
- [00:17:49.890]Quick selection guides located
- [00:17:51.540]in the NDOT Erosion and Sediment Control Pocket Guide
- [00:17:54.570]will identify the proper product selection
- [00:17:56.520]for the type of area you are treating.
- [00:17:58.800]There is a selection chart for both slope erosion control
- [00:18:01.860]and ditch and channel erosion control.
- [00:18:04.830]As we have talked about previously,
- [00:18:06.390]proper seed bed preparation is critical
- [00:18:07.937]of the success or failure of a blanket installation.
- [00:18:11.550]In this example, we can see where we have specific spots
- [00:18:14.640]where blanket has been installed
- [00:18:15.960]over larger clods of dirt that were not prepped correctly.
- [00:18:19.320]These clods tend the blanket,
- [00:18:20.730]leaving void spaces underneath the blanket,
- [00:18:23.220]which can lead to rills and gully erosion
- [00:18:25.110]underneath the blanket,
- [00:18:26.070]resulting in poor vegetated establishment.
- [00:18:28.860]As described earlier,
- [00:18:30.060]proper seed bed prep means
- [00:18:31.500]that we can have excellent mat-to-soil contact.
- [00:18:34.620]A blanket application
- [00:18:35.730]needs to have great soil contact over the entire area.
- [00:18:39.870]For slope applications,
- [00:18:41.370]the blanket attachment at the top of the slope is important.
- [00:18:44.640]Folding the blanket under the soil,
- [00:18:46.230]stapling in place, then compacting the soil
- [00:18:48.600]over the top of the attachment ensures
- [00:18:50.280]that sheet flows do not flow under the blanket
- [00:18:52.410]at the top of the slope.
- [00:18:54.150]Beginning the erosion process under the blanket.
- [00:18:57.120]Folding the top six inches of blanket together
- [00:18:59.760]and installing a double row
- [00:19:00.990]of staples closed together
- [00:19:02.310]across the entire edge is also accepted.
- [00:19:05.640]The critical success factor
- [00:19:06.960]for any blanket installation
- [00:19:08.370]is proper attachment to the ground.
- [00:19:10.650]This is done with staples.
- [00:19:12.360]For each installation type,
- [00:19:13.830]there is a corresponding staple pattern to use.
- [00:19:16.620]Contractors use different methods for installing staples,
- [00:19:19.860]but it is universal that the staple pattern
- [00:19:21.810]for each blanket type be followed as a minimum measure.
- [00:19:25.110]Any chance that you can utilize
- [00:19:26.430]more staples to ensure uniform mat-to-soil contact
- [00:19:29.280]will make the blanket installation much more effective.
- [00:19:32.460]For staple patterns and additional information,
- [00:19:35.100]refer to NDOT Standard Plan 501.
- [00:19:39.090]Failing to follow the NDOT specification
- [00:19:41.580]for staple patterns is a good way to invite erosion
- [00:19:44.010]to occur when material gets loose.
- [00:19:46.410]Failing to staple a blanket correctly
- [00:19:48.240]can lead to quick detachment
- [00:19:49.500]by even moderate windy conditions.
- [00:19:51.840]This installation may keep unraveling
- [00:19:53.670]if not quickly repaired,
- [00:19:55.380]leading to a complete reinstallation.
- [00:19:57.150]When determining if your blanket installation
- [00:19:59.220]meets NDOT specifications,
- [00:20:01.740]here's a few recommended observations to make.
- [00:20:04.740]One, look for proper staple placement.
- [00:20:07.830]With each type of blanket,
- [00:20:09.300]there is a corresponding staple pattern
- [00:20:11.100]which must be followed.
- [00:20:12.810]Blankets installed in swales
- [00:20:14.250]or ditches need more staples to keep the blanket in place.
- [00:20:17.580]Two, lift the blanket
- [00:20:19.380]to check if staples were installed correctly.
- [00:20:22.050]If the blanket is easily pulled away from the soil surface,
- [00:20:25.020]it likely needs more staples placed to secure it in place.
- [00:20:28.620]Use the required staple patterns as a minimum.
- [00:20:31.440]Don't skip, because a blanket failure
- [00:20:33.690]can happen easily underneath if improperly installed.
- [00:20:37.140]Three, if the installation has been done in a ditch
- [00:20:39.840]or swale, verify that staple check slots have been installed
- [00:20:43.860]and the blanket edges were properly secured.
- [00:20:46.740]Four, finally, verify the staple sizes
- [00:20:49.620]to the required specification.
- [00:20:52.260]Outlet protection can be composed
- [00:20:53.880]of rock riprap, Class 2 soil retention blankets,
- [00:20:57.270]transition matting and/or sod.
- [00:21:00.180]Outlet protection minimizes scour at the pipe outlet.
- [00:21:03.540]These materials and techniques
- [00:21:04.980]can be used at outlets of pipes,
- [00:21:06.540]drains, culverts, slope drains, diversion ditches,
- [00:21:09.900]swales, conduits, or channels.
- [00:21:13.350]Riprap outlet protection is made of coarse rock material,
- [00:21:16.890]commonplace on many construction sites
- [00:21:18.780]for stabilizing channels and basins.
- [00:21:21.270]The size of riprap material is specified
- [00:21:23.430]based on the anticipated flow characteristics
- [00:21:25.650]of the outlet, designed and specified by an engineer.
- [00:21:30.390]Other approved products
- [00:21:31.470]and specifications for outlet protection
- [00:21:33.510]are transition mats.
- [00:21:35.190]The first is a lightweight product,
- [00:21:36.810]which doesn't need heavy equipment for installation.
- [00:21:39.630]These are an alternative to rock riprap
- [00:21:41.430]that promotes grass and vegetation to grow up
- [00:21:43.950]through the open spaces in the matting,
- [00:21:46.140]creating a hard, armor-like bottom, but easier to maintain.
- [00:21:50.070]Be sure to follow the manufacturer's specifications
- [00:21:52.350]when installing transition mats.
- [00:21:54.000]Another new type of transition mat
- [00:21:55.710]is a tiled concrete block mat,
- [00:21:57.660]which is a vegetated concrete block mat
- [00:21:59.580]utilized for stabilizing slopes,
- [00:22:01.620]channels, low water crossings,
- [00:22:03.810]inlet and/or outlet protection and shorelines.
- [00:22:07.110]It consists of concrete blocks locked together
- [00:22:09.390]and embedded into a high strength geogrid.
- [00:22:12.120]There is 1.5 inch spacing between the blocks
- [00:22:14.610]that gives the mat flexibility
- [00:22:16.380]and allows for optional vegetation growth.
- [00:22:19.080]The mat is packaged in rolls,
- [00:22:20.700]making transporting and installing efficient.
- [00:22:22.830]For all types of outlet protection,
- [00:22:24.870]the most important installation keys
- [00:22:26.430]are to follow all engineering plans
- [00:22:28.080]and specifications for the project
- [00:22:30.270]and understand where drainage needs to go.
- [00:22:32.730]If stormwater drainage
- [00:22:33.900]is able to find an easier path, it will.
- [00:22:36.870]Don't allow water to flow anywhere
- [00:22:38.370]other than through the outlet protection.
- [00:22:41.070]Let's discuss silt checks, utilizes slope interruptions.
- [00:22:44.580]These essentially act as speed bumps
- [00:22:46.290]for runoff on longer forest slopes or back slopes,
- [00:22:49.920]dissipating the energy of storm water flows,
- [00:22:52.650]thus decreasing the potential and severity of erosion.
- [00:22:55.980]Silt checks on slopes are selected
- [00:22:57.810]or specified for slopes longer than 50 feet
- [00:23:00.780]and temporarily support vegetative growth
- [00:23:03.330]so slopes can achieve final stabilization requirements.
- [00:23:06.210]The key to installing silt checks for slope interruptions
- [00:23:08.910]is to make sure they're installed exactly on the contour.
- [00:23:12.360]In this example, we see a string
- [00:23:14.460]being used to mark the contour.
- [00:23:16.530]Any slope or angle
- [00:23:17.580]to the interruption will potentially cause a point
- [00:23:19.620]of concentration, causing a rile or gully to form.
- [00:23:23.280]For silt check installation
- [00:23:24.570]in conjunction with a blanket application,
- [00:23:26.880]stake the silt check on the downstream side.
- [00:23:29.490]Stake at two foot intervals.
- [00:23:31.980]Proper spacing is a critical success factor
- [00:23:34.170]for installing slope interruptions.
- [00:23:36.480]Almost without exception,
- [00:23:38.220]long slopes will specify
- [00:23:39.660]a 12-inch diameter wattle to be installed.
- [00:23:42.360]For typical three to one slopes,
- [00:23:43.950]spacing between each interruption will be 25 feet.
- [00:23:47.820]Another form of a slope interruption
- [00:23:49.470]would be vertical slope tracking,
- [00:23:51.390]done by creating a ground disturbance
- [00:23:52.980]with a dozer with sizable tracks,
- [00:23:55.290]driving up and down a slope in a vertical motion,
- [00:23:57.990]creating horizontal impressions,
- [00:23:59.970]essentially mini terraces.
- [00:24:01.980]This technique can be used in conjunction
- [00:24:03.900]with other BMPs such as seeding, mulch, or hydromulch.
- [00:24:07.650]Slope tracking is paid for by square yard.
- [00:24:10.980]Just by tracking a slope vertically with the right piece
- [00:24:13.440]of equipment, the erosion potential
- [00:24:15.360]can be cut by 50% on a three to one slope.
- [00:24:18.420]That's a tremendous improvement over doing nothing
- [00:24:20.520]with an impending rain forecast, 24 to 48 hours out.
- [00:24:24.210]It also gives a slope decent preparation
- [00:24:26.190]to install cover crop seeding,
- [00:24:28.170]as the small impressions capture
- [00:24:29.880]and hold the seed in place,
- [00:24:31.590]allowing for better germination potential.
- [00:24:34.620]In this example,
- [00:24:35.820]the slope has been fine-graded horizontally.
- [00:24:38.640]The cat tracks create express lanes for runoff
- [00:24:40.980]to run downhill, gathering speed, causing rile erosion,
- [00:24:45.180]and eventually gullies.
- [00:24:46.980]Whenever possible, take advantage
- [00:24:48.480]of the erosion control benefits of vertical slope tracking.
- [00:24:51.330]The last erosion control BMP
- [00:24:53.760]we will review is a temporary slope drain.
- [00:24:56.430]This work consists of constructing
- [00:24:57.900]a slope drain with any type of new or used
- [00:25:00.750]rigid or flexible pipe
- [00:25:02.400]that will adequately carry collected stormwater
- [00:25:04.620]from the toe of slope
- [00:25:05.580]to the ditch to prevent erosion on the slope.
- [00:25:08.310]Temporary slope drains should be sized
- [00:25:10.170]according to the amount of anticipated runoff
- [00:25:12.090]from the drainage area.
- [00:25:13.830]These drains shall be securely anchored
- [00:25:15.600]at the inlet, outlet, and along the slope
- [00:25:18.540]and velocity dissipation shall be placed
- [00:25:20.580]at the slope drain outlet to prevent scour.
- [00:25:22.770]Soil roughening is the practice of creating parallel strips
- [00:25:25.590]of rough soil for erosion control purposes.
- [00:25:28.560]These strips of roughened soil
- [00:25:29.940]can act is a slope eruption,
- [00:25:31.950]slowing down velocities of runoff water
- [00:25:33.990]on the contours of slopes or cross ditch bottoms.
- [00:25:37.080]They're made by using a field cultivator
- [00:25:38.880]or disk to make roughened areas
- [00:25:40.410]a minimum of eight feet wide,
- [00:25:42.090]at a minimum of three inches deep.
- [00:25:44.220]This work shall be initiated when the finish grade
- [00:25:46.440]is established for any location designated
- [00:25:48.329]in the contract for soil roughening.
- [00:25:50.910]It may also be used when work stops
- [00:25:52.650]for a period of time after locations have been rough graded.
- [00:25:56.490]Wrapping up Section 2,
- [00:25:57.660]we covered a lot of ground.
- [00:25:59.520]You should have a better understanding of NDOT specification
- [00:26:02.550]and installation requirements
- [00:26:03.900]for seeding and fertilizing methods
- [00:26:05.970]and soil stabilization methods like mulching, hydromulch,
- [00:26:09.480]soil retention blankets, outlet protection,
- [00:26:12.750]including rock riprap, and transition mats, silt checks
- [00:26:15.720]for slopes using wattles,
- [00:26:17.430]slope tracking, temporary slope drains, and soil roughening.
- [00:26:21.840]Now, close the slideshow and return to the course menu
- [00:26:24.480]and take the quick five question quiz
- [00:26:26.130]to move on to Section 3.
The screen size you are trying to search captions on is too small!
You can always jump over to MediaHub and check it out there.
Log in to post comments
Embed
Copy the following code into your page
HTML
<div style="padding-top: 56.25%; overflow: hidden; position:relative; -webkit-box-flex: 1; flex-grow: 1;"> <iframe style="bottom: 0; left: 0; position: absolute; right: 0; top: 0; border: 0; height: 100%; width: 100%;" src="https://mediahub.unl.edu/media/22566?format=iframe&autoplay=0" title="Video Player: Erosion Control Practices" allowfullscreen ></iframe> </div>
Comments
0 Comments