- [00:00:01.660]Project coordination meetings.
- [00:00:06.370]Our project coordination meetings are designed
- [00:00:08.220]to increase project awareness
- [00:00:09.680]for the local public agency projects, identify risks,
- [00:00:13.880]communicate project changes, and coordinate action plans
- [00:00:16.890]at key project delivery points.
- [00:00:20.810]We've got eight total types
- [00:00:22.490]of project coordination meetings,
- [00:00:23.890]although two of them are optional.
- [00:00:26.770]But throughout the life cycle of a project,
- [00:00:29.970]we will go through a PCM 0, 20, 30, 35, 50, 70, 80, and 90.
- [00:00:36.480]And we'll talk about each of these meetings more
- [00:00:40.030]in the following slides.
- [00:00:42.700]PCM O is going to be our pre-red flag meetings.
- [00:00:45.790]So the purpose of this meeting is
- [00:00:47.160]to provide a high-level overview of the proposed project
- [00:00:49.940]with the goal of identifying known risks upfront
- [00:00:53.660]so we kind of know what we're going to have to deal with.
- [00:00:57.340]And then the goal of these meetings are
- [00:01:00.570]to gather necessary information
- [00:01:02.140]to aid in the development of the scope of services
- [00:01:05.310]for both PE and NEPA,
- [00:01:07.030]and then provide enough information for the consultant
- [00:01:09.700]to develop the project description, project details,
- [00:01:12.560]and purpose and need.
- [00:01:14.810]Our PCM 20 is the project introduction meeting.
- [00:01:18.510]So this one's going to serve as the kickoff meeting
- [00:01:21.010]for the entire project.
- [00:01:22.710]At this meeting, we'll discuss the NDOT-530, the NDOT-53,
- [00:01:27.610]the project description, details, and purpose and need.
- [00:01:31.090]It's important to know, in order to hold this meeting,
- [00:01:34.630]we have to have an NDOT-530,
- [00:01:36.980]which is the LPA programming request,
- [00:01:39.110]and an approved NDOT-53,
- [00:01:42.180]which is the probable class of NEPA action form.
- [00:01:45.480]The goal for the PCM 20 is to review project concerns
- [00:01:49.180]and talk about the initial design.
- [00:01:53.010]Our PCM 30 is going to be our pre-plan-in-hand meeting.
- [00:01:55.860]The purpose of this one is to discuss any changes
- [00:01:58.710]to the project description and details,
- [00:02:01.450]talk about any issues or concerns related to design
- [00:02:04.360]or environmental reviews, and discuss potential conflicts
- [00:02:07.830]that should be verified at the plan-in-hand visit.
- [00:02:10.770]Normally we have this one about a week
- [00:02:12.620]before our plan-in-hands.
- [00:02:14.470]That way everything is fresh in our minds
- [00:02:17.220]when we go out on site.
- [00:02:19.510]The goal is to identify any sensitive environmental areas,
- [00:02:23.290]discuss design constructability concerns,
- [00:02:25.780]and provide guidance ahead of the plan-in-hand field visit
- [00:02:28.410]and PCM 35.
- [00:02:32.545]The PCM 35 meeting is going to be
- [00:02:34.720]the post-plan-in-hand meeting.
- [00:02:37.820]So the purpose of this one is
- [00:02:39.440]to verify that all the PCM 30
- [00:02:41.190]and plan-in-hand comments have been addressed.
- [00:02:43.800]We'll talk about any project design issues or modifications
- [00:02:47.180]that were identified during the plan-in-hand field visit,
- [00:02:50.060]discuss project constructability issues
- [00:02:52.290]that need to be captured
- [00:02:53.310]in project environmental documentation
- [00:02:55.740]or that may require further coordination
- [00:02:57.650]with any environmental agencies.
- [00:03:00.530]And this meeting also initiates
- [00:03:03.020]the documentation of environmental reviews
- [00:03:05.030]and approval phase of the project.
- [00:03:08.970]So the goal for this one is going to be
- [00:03:10.730]to present updated design plans after our plan-in-hand
- [00:03:14.250]with limits of construction,
- [00:03:16.380]changes to the project description, product details,
- [00:03:18.680]and purpose and need also, updated from previously.
- [00:03:23.370]And then the limits-of-construction are considered complete
- [00:03:25.960]at this stage.
- [00:03:30.000]The PCM 50 is going to be one of those optional ones
- [00:03:32.260]I did mention earlier.
- [00:03:34.030]This is going to be pre-NEPA approval.
- [00:03:36.540]So the purpose of this one is to be used
- [00:03:38.540]if the project has had significant changes since the PCM 35,
- [00:03:43.030]or it could be used
- [00:03:44.110]if the project has been inactive for a long period of time
- [00:03:46.750]and we just want to catch people up
- [00:03:48.090]and get them on the same page.
- [00:03:50.510]The goal for this one is
- [00:03:52.020]to provide an update of any significant project changes
- [00:03:55.080]to the project delivery team,
- [00:03:57.460]just make sure everybody knows what's going on
- [00:03:59.510]with the project.
- [00:04:02.900]The PCM 70 is the right-of-way re-evaluation meeting.
- [00:04:06.890]So the purpose of this one is to kickoff
- [00:04:08.810]the right-of-way re-evaluation phase.
- [00:04:10.960]So at this one, we'll discuss final plans
- [00:04:13.170]and any potential changes needed
- [00:04:14.770]for the environmental document.
- [00:04:16.710]An approved environmental document is required
- [00:04:19.070]prior to this meeting
- [00:04:19.950]as well as approved right-of-way plans.
- [00:04:23.200]The goal for this meeting is
- [00:04:24.310]to verify the right-of-way design plans
- [00:04:26.110]and kickoff the re-eval of the NEPA document
- [00:04:28.490]for the right-of-way obligation.
- [00:04:31.720]The PCM 80 is going to be this other optional one
- [00:04:34.970]that I mentioned at the beginning.
- [00:04:36.250]It's our PS&E re-evaluation meeting.
- [00:04:38.930]The purpose of this one is that it occurs near
- [00:04:40.880]the completion of right-of-way acquisition
- [00:04:43.200]and will be used if the project has had significant changes
- [00:04:46.840]as a result of the right-of-way negotiation process.
- [00:04:49.830]This one can also be used if the project has been inactive
- [00:04:53.280]for a significant period of time.
- [00:04:55.640]The goal for this one is going to be
- [00:04:57.320]to review changes made during the right-of-way acquisition
- [00:04:59.830]and kickoff the NEPA re-eval for PS&E turn-in.
- [00:05:04.450]Our final project coordination meeting
- [00:05:06.280]before the PS&E turn-in going to be the PCM 90,
- [00:05:09.810]which is the green sheet review.
- [00:05:11.540]The purpose of this one is
- [00:05:12.650]to ensure that final design plans are consistent
- [00:05:14.830]with approved environmental documentation
- [00:05:17.260]and commitments and mitigation have been included
- [00:05:19.460]in the green sheet for use in contracting.
- [00:05:22.700]One thing you need to know about this one is
- [00:05:24.620]that a draft green sheet is required
- [00:05:26.600]in order to hold this meeting.
- [00:05:29.180]The goal for this one is
- [00:05:30.130]to verify final design plans are ready
- [00:05:31.930]to be submitted to PS&E,
- [00:05:33.330]and then also we'll review the green sheet
- [00:05:35.620]during this meeting as well.
The screen size you are trying to search captions on is too small!
You can always jump over to MediaHub and check it out there.
Log in to post comments
Embed
Copy the following code into your page
HTML
<div style="padding-top: 56.25%; overflow: hidden; position:relative; -webkit-box-flex: 1; flex-grow: 1;"> <iframe style="bottom: 0; left: 0; position: absolute; right: 0; top: 0; border: 0; height: 100%; width: 100%;" src="https://mediahub.unl.edu/media/17270?format=iframe&autoplay=0" title="Video Player: Online RC Refresher Training: Module 1" allowfullscreen ></iframe> </div>